A new waste to energy plant called KEBAG Enova Emmenspitz, will be built in Zuchwil, Canton Solotthurn, Switzerland. This new plant has two combustion lines which will be used to process 221.000 tonnes of source-separated municipal and commercial waste a year to generate up to 53.7 MW of thermal energy that will be fed into the respective grid as electricity or district heat.
GHENOVA scopeofworks:
Structuredetailengineering.
Ghenova is responsible of the engineering and design of the steel structure for combustion and boiler area:
Engineering: Structural calculation including optimizing of steelwork profiles, detail calculation of all connections, temporary work calculation, engineering drawings and floor covering drawings.
Workshop documentation: Single part and assembly/delivery unit drawings, material lists, NC files and Excel list for LMS data system
Erection documentation: Erection drawings, cube drawings, lifting unit (LU) drawings and material lists.